Man it's nice to see you here "Red Death." ;-)
I really needed you down here around the end of January, a few years back I placed a 48 strand for US Sugar, they advised me it could be just dropped into a drainage ditch which I did.
Now the reason that was done is because CL wanted to set the DEMARC at the property line and advised USS to hire a contractor to extend it to the refinery which I was contracted to do.
Well early this year they decided to dig the drainage ditch deeper and guess what?
Their contractor wrecked 3.4 KF of fiber.
Now I still had the reel of fiber I found on the "side of the road" and do have a Fujikura fusion splicer system that was abandoned when the temps of Construction where laid off, at Davie Blvd, but I really don't know how to properly use it.
The first time when I placed the fiber I hired a contractor working out here on a L3 project, he knocked both ends in less than a day, doing it myself took me 3 days combined with a lot of colorful words,
Fusion splicing looks easy if one knows what they are doing, which I didn't.
,